University Village Park

Construction stormwater treatment system situated in the parking lot at University Village in Seattle

Project Information

This small-footprint system was installed for sump dewatering and stormwater runoff treatment on a 1-acre construction site at The University Village in Seattle, WA.

The project encountered a much lower dewatering flowrate than anticipated, shortening the duration of the project.

Clear Water trained and certified an employee of the contractor, Mid Mountain Construction, to become a CESF operator.

Project Details

  • Project Name: University Village Park
  • Client Name:  Mid Mountain Construction
  • Location:  Seattle, WA
  • Technology:  CESF
  • Flow Rate: 150 GPM
  • Constituents:  Turbidity/pH
  • Operational: December 2019-Feburary 2020
  • Gallons Treated to Date: 200,000 Gallons